London Fields Lido closed on 9th April 2017 for the essential repairs to the pool tank. During the closure the changing rooms and reception area are also being renovated.

Progress Update

The pool tank tiles have been removed and work is currently being undertaken to expose the pool slab before work to retile the pool tank can start. A canpy has been built over the pool so that the works can continue when it rains. To prepare for the construction of the new recpetion area and changing rooms various walls and ceilings have been taken down and the floor slab is being dug out for new drainage. The work to expose the pool slab and the digging out of the changing room slab are both taking longer than anticipated due to the construction materials used. However, the contractor has bought heavy duty equipment onto site to spped up this work and we are still hopeful at this stage that the work will be completed by late summer 2017.